Session 0 — Agile Foundations & Tool Setup (Slack + Jira + GitHub)

Format

2h theory + 2h lab

  • Team size: 10 (each team = a mini‑company inside TechOps Inc.)
  • Tools: Slack, Jira, GitHub
  • Output: Working Slack workspace + Jira project + Sprint‑1 plan

Objectives

  • Explain Agile values & principles, and the differences between Scrum and Kanban in the context of IT Infrastructure & DevOps.
  • Set up team collaboration tools: Slack (ChatOps) and Jira (Agile project management).
  • Create a syllabus‑mapped backlog and plan Sprint 1
  • Establish working agreements, roles, and a definition of done (DoD) for the team.
  • Prepare a GitHub team repo structure that will be used throughout the course.

Summary (Agile for Infra & DevOps)

Agile emerged to counter rigid, plan‑heavy delivery models that struggled with uncertainty. In Dev and Ops contexts, Agile is less about speed for its own sake and more about short feedback loops, visibility, and continuous improvement. We’ll use Agile to coordinate complex work across infrastructure, cloud, and DevOps pipelines.

Agile values emphasize individuals & interactions, working solutions, customer collaboration, and responsiveness to change. In our setting, “customer” = your stakeholders: internal teams, instructors, and demo audiences. Principles like frequent delivery, technical excellence, and sustainable pace map well to infrastructure work: small increments (e.g., baseline VM image), validated frequently (checkpoints), and continuously improved (automation).

Scrum fits when you have a well‑defined increment and cadence: plan a sprint (2–3 weeks), hold a daily stand‑up (async in Slack), and aim for a potentially shippable increment (e.g., Infra Blueprint by Session 9). Roles are flexible here: a Project Lead plays Scrum Master‑like facilitation; the Instructor is close to Product Owner; the team is the cross‑functional developers (DevOps, Cloud, Security, Monitoring, Storage/Network).

Kanban suits ongoing ops (tickets, incidents, enhancements). You’ll use Kanban columns (To Do → In Progress → Review → Done) with WIP limits to prevent overload while doing labs and hardening.

In DevOps culture, ChatOps (tooling + conversation) turns Slack into the central nervous system: GitHub PRs, Jenkins builds, monitoring alerts, and Jira updates surface in channels so decision‑making is transparent and fast. Jira anchors planning and tracking: epics for phases (Infra, Cloud, DevOps, CI/CD, Security/HA), stories for sessions, and tasks for lab steps. Your Definition of Done ensures quality (docs/screenshots/automation checked in, peer review done, Jira story moved to Done, Slack summary posted).

Key benefits you’ll feel immediately: - Visibility: everyone sees who’s doing what, what’s blocked, and what’s next.
- Traceability: each lab deliverable ties to a Jira story and a GitHub PR.
- Incremental progress: you’ll produce checkpoints that layer into the final demo.


Practical Application (TechOps Inc. Simulation)

Scenario: You’ve just joined TechOps Inc. as a 10‑person platform team. You have two weeks to deliver the project Infra Blueprint. Today you will create your communication hub, project board, repo, and a working plan for Sprint‑1.


Lab Guide (2h)

A. Slack Workspace (ChatOps) — 25 min

  1. Create or join the course Slack workspace.
  2. Create channels:
  3. #announcements (read‑only for instructors)
  4. #helpdesk (Q&A with instructors)
  5. #team-<company-name> (private team channel)
  6. Optional cross‑team: #devops, #cloud, #storage, #monitoring
  7. Add integrations (you can wire these fully in later sessions):
  8. GitHub: repo notifications to #team-<company-name>
  9. Jira: story updates → #team-<company-name>
  10. Pin a Team Charter (copy, edit, and post):
  11. Team name, members & roles (Cloud Architect, SysAdmin, DevOps x2, Developers x2, Security, Monitoring, Storage/Network, Project Lead)
  12. Working hours, response times
  13. Stand‑up time (async template: Yesterday / Today / Blockers)
  14. Definition of Done (see template below)

DoD template (pin this): - Code/config committed with README and comments
- Steps reproducible; credentials redacted; screenshots added
- PR raised & reviewed by ≥1 peer
- Jira story moved to Done with link to PR and short summary
- Slack update posted (#team-...): what changed, who reviews, where to test


B. Jira Project — 35 min

  1. Create a Jira project: TechOps Inc. – Company
  2. Create Epics (map to course phases):
  3. Infra Foundations (S6–S9)
  4. Virtualization & Cloud (S10–S13)
  5. DevOps Foundations (S14–S17)
  6. CI/CD & Monitoring (S18–S20)
  7. Security & HA (S21–S23)
  8. Create User Stories for Sprint‑1 (Sessions 6–9). Suggested set:
  9. S6: Baseline VM image (Linux/Windows), snapshot strategy
  10. S7: Data center layout & constraints doc
  11. S8: NAS (TrueNAS CORE) for team file sharing
  12. S9: SAN (iSCSI) for VM cluster
  13. Break stories into Tasks (examples):
  14. Download Ubuntu LTS ISO; create VM (2 vCPU/4GB/40GB)
  15. Install base packages + updates; create baseline-v1 snapshot
  16. Deploy TrueNAS VM; configure share; test from team VM
  17. Configure iSCSI target; connect initiator; validate block storage
  18. Add Definition of Done at project level (and link to the Slack post).
  19. Set Sprint‑1 dates (cover S6–S9 timeline); assign story owners; estimate points.

(Optional) CSV import: you can prepare a CSV of stories/tasks to import into Jira if you prefer. Keep a copy in docs/assets/Jira-backlog/.


C. GitHub Team Repo — 35 min

  1. Create a repo (private or internal): techops-<company-name>.
  2. Add this starter structure:
    ├── infra/
    │ ├── vm-baseline/
    │ ├── nas-truenas/
    │ └── san-iscsi/
    ├── cloud/
    ├── app/
    ├── cicd/
    ├── monitoring/
    ├── security/
    └── docs/
    ├── lab-notes/
    └── diagrams/
    
  3. Add a root README.md with:
  4. Team roster & roles
  5. How to clone & run labs
  6. Links to Slack channel & Jira board
  7. Create a docs/lab-notes/session-06.md file and add checklists for VM setup.
  8. Set up branch protection (require PR review by at least one teammate).
  9. Connect GitHub → Slack notifications to your team channel.

D. Sprint Planning — 25 min

  1. Capacity: note each member’s realistic hours for the sprint.
  2. Prioritize stories for S6–S9; split if too big (aim for 1–3 days per story).
  3. Assign owners; confirm acceptance criteria align with DoD.
  4. Add risk/assumption notes: ISO availability, network limits, hardware quotas.
  5. Post the Sprint plan summary in Slack and pin it.

Checkpoints (end of session)

  • Slack workspace & team channel ready; Team Charter pinned
  • Jira project created with Epics, Stories (S6–S9), Tasks, Sprint‑1 dates
  • GitHub repo created with agreed folder structure + initial README
  • Definition of Done documented and referenced in both Slack & Jira
  • Sprint‑1 plan posted in Slack (owner per story + acceptance criteria)

Quick Quiz (knowledge check)

Which Agile practice best ensures visibility of daily progress and blockers?
  • Daily stand‑ups (async in Slack)
  • Quarterly release planning
  • Post‑mortems only after failures
  • Annual performance reviews
In this course, who is closest to the Product Owner role?
  • Instructor (defining outcomes & acceptance)
  • Security Engineer
  • Project Lead
  • Cloud Architect
What belongs in our Definition of Done (pick all that apply)?
  • Reproducible steps & docs in repo
  • PR reviewed by a teammate
  • Jira story moved to Done with links
  • Only a verbal confirmation in class

Deliverables (to be graded)

  1. Slack: Link to team channel + pinned Team Charter & DoD
  2. Jira: Project URL + screenshot of Sprint‑1 board
  3. GitHub: Repo URL + screenshot of repo structure
  4. Sprint‑1 plan: Short note in Slack with owners & dates